Shift in Plans

Plan Set Cover

Plans for the Grandview house were submitted in mid-November 2016. Four months and 10 days later we received permit approval – with no changes requested from the building department. Either they were really detailed plans or once the fourth month comes, the building department must approve the permit.

The permit delay does not allow enough schedule to complete the home in time for the 2017 Parade of Homes.

Construction of the home will be shifted to 2018 tentatively scheduled for spring and completion for the Parade of Homes.